Overview & Fundamental Concept
Time and Work is one of the most intellectually rigorous and reliable 10-mark questions in the RIMC Mathematics Paper (Paper I, 200 Marks, 90 Minutes). Prescribed under Item 23 of Chapter 8 in the official RIMC brochure, questions in this module appear regularly across both Part A (5 Marks) and Part B (10 Marks). The syllabus evaluates a candidate's mastery over fractional daily work rates, pairwise working pairs $(A+B, B+C, C+A)$, workers departing prior to completion or joining mid-task, alternate-day cyclic schedules, proportional division of wages based on work done, and fluid dynamics of inlet pipes and drainage leaks in cisterns. In the descriptive exam booklet, RIMC examiners demand formal declarations of daily rates ('Work done by A in 1 day = 1/a'), explicit residual work calculations ($W_{\text{remaining}} = 1 - W_{\text{done}}$), and boxed final answers with standard units (days, hours, rupees).
| Syllabus Item | Prescribed Scope | Exam Relevance & Pedagogical Objective |
|---|---|---|
| Item 23 | Time and work: Daily work rates, combined work, efficiency, pipes and cisterns, and wage distribution | Core brochure syllabus item. Tests reciprocal proportional reasoning, multi-rate aggregation, dynamic schedule adjustments, and work-based compensation. |
In the unitary method of Time and Work, Total Work is always defined as exactly $1$ complete unit (representing 100% of the project).
The Fundamental Reciprocal Principle: Time taken and the work rate per unit time are reciprocals of each other:
$$\text{If a person completes a piece of work in } n \text{ days, then in } 1 \text{ day he completes } \mathbf{\frac{1}{n}} \text{ part of the work.}}$$
$$\text{Conversely, if a person completes } \frac{1}{n} \text{ part of the work in } 1 \text{ day, he will take } \mathbf{n} \text{ days to finish the entire work.}}$$
Combined Work Rates of Multiple Independent Workers
- Two Workers (A and B): If A takes $a$ days and B takes $b$ days:
$$(A + B)\text{'s } 1\text{ day's work} = \frac{1}{a} + \frac{1}{b} = \frac{a + b}{ab}$$
$$\text{Time taken together} = \frac{ab}{a + b}\text{ days}$$ - Three Workers (A, B, and C):
$$(A + B + C)\text{'s } 1\text{ day's work} = \frac{1}{a} + \frac{1}{b} + \frac{1}{c} = \frac{bc + ca + ab}{abc}$$
$$\text{Time taken together} = \frac{abc}{ab + bc + ca}\text{ days}$$
A classic RIMC 10-mark problem gives the combined rates of pairs of workers: $(A+B)$ finishes in $x$ days, $(B+C)$ in $y$ days, and $(C+A)$ in $z$ days.
Summing all three pairs yields twice the combined capacity:
$$2(A + B + C)\text{'s } 1\text{ day's work} = \frac{1}{x} + \frac{1}{y} + \frac{1}{z}$$
$$(A + B + C)\text{'s } 1\text{ day's work} = \frac{1}{2} \left( \frac{1}{x} + \frac{1}{y} + \frac{1}{z} \right)$$
To find the individual time taken by any single worker, subtract the appropriate pair from $(A + B + C)$:
• A's 1 day's work $= (A + B + C) - (B + C)$
• B's 1 day's work $= (A + B + C) - (C + A)$
• C's 1 day's work $= (A + B + C) - (A + B)$
In advanced practical scenarios, the composition of the workforce alters dynamically during execution:
Workers Leaving Before Completion
When worker B departs $k$ days before the project is scheduled to finish, let the total project duration be $T$ days:
- Worker A works for the entire $T$ days, while B works for only $(T - k)$ days.
- Governing equation: $T \times \left(\frac{1}{a}\right) + (T - k) \times \left(\frac{1}{b}\right) = 1$.
Alternate Day Working Schedules
When A works on Day 1, B works on Day 2, A on Day 3, etc.:
- A full cycle consists of $2\text{ days}$.
- Work accomplished in one 2-day cycle $= \frac{1}{a} + \frac{1}{b}$.
- Determine the maximum number of complete 2-day cycles that can fit into $1$ unit of work, and evaluate the remaining fraction on Day $(2k + 1)$ with worker A.
Efficiency & Division of Wages
Wages are distributed strictly in proportion to the total work completed by each individual (or their daily work rate if all worked for the same number of days):
- Ratio of Wages $= (A\text{'s total work}) : (B\text{'s total work}) : (C\text{'s total work})$.
- Efficiency is inversely proportional to time taken: $\frac{\text{Efficiency}_A}{\text{Efficiency}_B} = \frac{\text{Time}_B}{\text{Time}_A}$.
Pipes and Cisterns problems follow the exact same mathematical laws as human workers, with one vital distinction: leakage or drainage pipes perform NEGATIVE work.
• Inlet Pipe: Fills the tank $\implies$ Work Rate is positive ($+\frac{1}{t_{\text{in}}}$).
• Outlet / Waste Pipe / Leak: Empties the tank $\implies$ Work Rate is negative ($-\frac{1}{t_{\text{out}}}$).
• Net Filling Rate:
$$\text{Net Rate per hour} = \left( \frac{1}{t_{\text{in}}} - \frac{1}{t_{\text{out}}} \right)$$
Topper Strategy & Descriptive Step Breakdown
In RIMC, clear step-by-step layout is essential. Write down all given values, declare formulas before substitution, and conclude with full sentences with proper units.
In RIMC Stage-I, answers without step justification receive only 20-30% of total marks even if the numeric answer is correct. Follow this strict 4-tier layout on every question:
State the individual time taken and declare the reciprocal 1-day (or 1-hour) work rates for each person/pipe.
Given:\nTime taken by A alone $= 10\text{ days} \implies \text{A's 1 day's work} = \frac{1}{10}$\nTime taken by B alone $= 15\text{ days} \implies \text{B's 1 day's work} = \frac{1}{15}$
Sum the fractional rates, find LCM of denominators, and compute the work completed during the joint phase.
$$(A + B)\text{'s 1 day's work} = \frac{1}{10} + \frac{1}{15} = \frac{3 + 2}{30} = \frac{5}{30} = \frac{1}{6}$$
$$\text{Work done by (A + B) in 3 days} = 3 \times \frac{1}{6} = \frac{1}{2}$$
Subtract Phase-1 work from 1 to obtain remaining work, then divide by the surviving worker's daily rate.
$$\text{Remaining Work} = 1 - \frac{1}{2} = \frac{1}{2}$$
$$\text{Time taken by A to finish} = \frac{\text{Remaining Work}}{\text{A's daily rate}} = \frac{1/2}{1/10} = \frac{1}{2} \times 10 = 5\text{ days}$$
State the final time clearly in words and enclose the answer in a neat box.
$$\mathbf{\text{Answer: A will finish the remaining work in } 5\text{ days.}}$$
Key Formulas & Conversion Cheat Sheet
Fraction of project completed in a single unit of time.
Joint work rate of two individuals.
Product over sum formula for two workers.
Sum of individual fractional rates.
Derives 3-worker rate from pair combinations.
Work left to be completed by surviving workers.
Combines filling inlets with draining outlets.
Multi-variable workforce, time, and output balance.
Work done by B in $1\text{ day} = \frac{1}{15}$.
Work done by $(A + B)$ in $3\text{ days}$:
$$W_3 = 3 \times \frac{1}{6} = \frac{3}{6} = \frac{1}{2}$$
Time taken by A to complete $\frac{1}{2}$ work:
$$t = \frac{\text{Remaining Work}}{\text{A's 1 day's rate}} = \frac{1/2}{1/10} = \frac{1}{2} \times 10 = \mathbf{5\text{ days}}$$
$$\mathbf{\text{Answer: A will finish the remaining work in } 5\text{ days.}}$$
$$(B + C)\text{'s 1 day's work} = \frac{1}{15}$$
$$(C + A)\text{'s 1 day's work} = \frac{1}{20}$$
Adding all three equations:
$$2(A + B + C)\text{'s 1 day's work} = \frac{1}{12} + \frac{1}{15} + \frac{1}{20}$$
$\text{LCM}(12, 15, 20) = 60$:
$$= \frac{5 + 4 + 3}{60} = \frac{12}{60} = \frac{1}{5}$$
$$\text{Time taken by all three together} = 10\text{ days}$$
$$= \frac{1}{10} - \frac{1}{15} = \frac{3 - 2}{30} = \frac{1}{30}$$
$$\text{Time taken by A alone} = \mathbf{30\text{ days}}$$
$$\mathbf{\text{Answer: Together = } 10\text{ days}; \quad \text{A alone = } 30\text{ days}}$$
Day 2: B works and does $\frac{1}{12}$ of the work.
Work completed in one $2\text{-day cycle}$:
$$W_{\text{cycle}} = \frac{1}{16} + \frac{1}{12} = \frac{3 + 4}{48} = \frac{7}{48}\text{ of total work}$$
Since $7 \times 6 = 42 < 48$ and $7 \times 7 = 49 > 48$, take $k = 6\text{ full cycles}$.
In $6\text{ cycles}$ (which is $6 \times 2 = 12\text{ days}$):
$$\text{Work completed in 12 days} = 6 \times \frac{7}{48} = \frac{42}{48} = \frac{7}{8}$$
$$\text{Remaining Work} = 1 - \frac{42}{48} = \frac{6}{48} = \frac{1}{8}$$
A's daily capacity $= \frac{1}{16} = \frac{3}{48}$.
Since remaining work $\frac{6}{48} > \frac{3}{48}$, A works the entire 13th day and completes $\frac{3}{48}$ work.
$$\text{Work left at end of Day 13} = \frac{6}{48} - \frac{3}{48} = \frac{3}{48} = \frac{1}{16}$$
On Day $14$, it is B's turn.
B's capacity $= \frac{1}{12} = \frac{4}{48}$.
Time taken by B to finish $\frac{3}{48}$ work:
$$t_B = \frac{3/48}{4/48} = \frac{3}{4}\text{ day}$$
$$\text{Total Time Taken} = 12 + 1 + \frac{3}{4} = \mathbf{13\frac{3}{4}\text{ days}}$$
$$\mathbf{\text{Answer: The project will be completed in } 13\frac{3}{4}\text{ days.}}$$
Work done by $(A + B) = \frac{19}{23}$.
Since $(A + B + C) = 1$, work done by C alone is:
$$\text{Work of C} = 1 - (A + B) = 1 - \frac{19}{23} = \mathbf{\frac{4}{23}}$$
Work done by A alone is:
$$\text{Work of A} = 1 - (B + C) = 1 - \frac{8}{23} = \mathbf{\frac{15}{23}}$$
Now compute B's share:
$$\text{Work of B} = 1 - (\text{Work of A} + \text{Work of C}) = 1 - \left(\frac{15}{23} + \frac{4}{23}\right) = 1 - \frac{19}{23} = \mathbf{\frac{4}{23}}$$
Check: $\frac{15}{23} + \frac{4}{23} + \frac{4}{23} = \frac{23}{23} = 1$ (Verified!).
$$\text{Share of A} = \frac{15}{23} \times 5290 = 15 \times 230 = \mathbf{₹ 3,450}$$
$$\text{Share of B} = \frac{4}{23} \times 5290 = 4 \times 230 = \mathbf{₹ 920}$$
$$\text{Share of C} = \frac{4}{23} \times 5290 = 4 \times 230 = \mathbf{₹ 920}$$
Check: $3450 + 920 + 920 = ₹ 5,290$.
$$\mathbf{\text{Answer: A gets } ₹\;3,450; \quad \text{B gets } ₹\;920; \quad \text{C gets } ₹\;920}$$
A worked for the entire duration of $T\text{ days}$.
B left $5\text{ days}$ before completion, so B worked for $(T - 5)\text{ days}$.
B's 1 day's work $= \frac{1}{30}$.
Total Work $= 1$:
$$\text{Work done by A} + \text{Work done by B} = 1$$
$$T \times \left(\frac{1}{20}\right) + (T - 5) \times \left(\frac{1}{30}\right) = 1$$
$$60 \times \left(\frac{T}{20}\right) + 60 \times \left(\frac{T - 5}{30}\right) = 60 \times 1$$
$$3T + 2(T - 5) = 60$$
$$3T + 2T - 10 = 60$$
$$5T = 60 + 10 = 70 \implies T = \frac{70}{5} = \mathbf{14\text{ days}}$$
B worked for $14 - 5 = 9\text{ days}$: $9 \times \frac{1}{30} = \frac{3}{10}$ work.
Total work $= \frac{7}{10} + \frac{3}{10} = \frac{10}{10} = 1$ (Verified!).
$$\mathbf{\text{Answer: The entire work was completed in } 14\text{ days.}}$$
(a) If all three pipes are opened simultaneously when the reservoir is empty, how long will it take to fill the reservoir completely?
(b) If Pipe C is kept open for the first $4\text{ hours}$ and then closed, in how much additional time will Pipes A and B fill the remaining reservoir?
Pipe B: fills $\frac{1}{16}$ reservoir/hour ($+1/16$).
Pipe C: empties $\frac{1}{8}$ reservoir/hour ($-1/8$).
$$\text{Net Rate} = \frac{1}{12} + \frac{1}{16} - \frac{1}{8}$$
$\text{LCM}(12, 16, 8) = 48$:
$$\text{Net Rate} = \frac{4 + 3 - 6}{48} = \frac{7 - 6}{48} = \frac{1}{48}\text{ reservoir per hour}$$
$$\text{Total Time to fill (Part a)} = \frac{1}{1/48} = \mathbf{48\text{ hours}}$$
$$\text{Water filled in 4 hours} = 4 \times \frac{1}{48} = \frac{4}{48} = \frac{1}{12}$$
$$\text{Remaining reservoir to be filled} = 1 - \frac{1}{12} = \frac{11}{12}$$
$$\text{Combined Rate of (A + B)} = \frac{1}{12} + \frac{1}{16} = \frac{4 + 3}{48} = \frac{7}{48}$$
$$\text{Additional Time} = \frac{\text{Remaining Volume}}{\text{Rate of (A + B)}} = \frac{11/12}{7/48} = \frac{11}{12} \times \frac{48}{7} = \frac{11 \times 4}{7} = \frac{44}{7} = \mathbf{6\frac{2}{7}\text{ hours}}$$
$$\mathbf{\text{Answer: (a) } 48\text{ hours}; \quad \text{(b) Additional time = } 6\frac{2}{7}\text{ hours (or } 6\text{ h } 17\text{ m } 9\text{ s})}}$$
RIMC Practice & Drill Exercises
Attempt these questions on paper following proper step-wise conventions, then click Reveal Solution to verify your answers.
A alone finishes in $20\text{ days}$.
Together: $2x + x = 3x = \frac{1}{14} \implies x = \frac{1}{42}$.
A alone takes $21\text{ days}$.
$$\text{Fraction Left} = 1 - \frac{7}{15} = \frac{8}{15}$$
Remaining work $= 1 - \frac{1}{3} = \frac{2}{3}$.
$$\text{Time} = \frac{2/3}{5/36} = \frac{2}{3} \times \frac{36}{5} = \frac{24}{5} = 4.8\text{ days}$$
Hour 2: $(A + C)$ open $\implies \frac{1}{12} + \frac{1}{20} = \frac{5 + 3}{60} = \frac{8}{60} = \frac{2}{15}$.
Remaining $= 1 - \frac{51}{60} = \frac{9}{60}$.
In 7th hour, $(A + B)$ operates and fills exactly $\frac{9}{60}$.
Total time $= 6 + 1 = 7\text{ hours}$.
Multiply by $\text{LCM}(10, 20, 30) = 60$:
$$\text{Ratio} = 6 : 3 : 2$$
Sum of terms $= 6 + 3 + 2 = 11$.
B $= \frac{3}{11} \times 1100 = ₹ 300$.
C $= \frac{2}{11} \times 1100 = ₹ 200$.
A works for $6\text{ days}$.
B works for $(T - 6)\text{ days}$.
C works for the entire $T\text{ days}$.
Multiply by $\text{LCM}(24, 32, 64) = 192$:
$$8(6) + 6(T - 6) + 3T = 192$$
$$48 + 6T - 36 + 3T = 192 \implies 9T + 12 = 192$$
Pipe B: $45\text{ mins} \implies \text{Rate} = \frac{1}{45}\text{ per min}$.
$$30 \times \frac{2}{75} + t \times \frac{1}{45} = 1$$
$$\frac{60}{75} + \frac{t}{45} = 1 \implies \frac{4}{5} + \frac{t}{45} = 1$$
Leak + Inlet empties in $12\text{ hours} \implies -\frac{1}{12}\text{ per hour}$.
$$\text{Inlet Rate} = \left(-\frac{1}{12}\right) - \left(-\frac{1}{8}\right) = \frac{1}{8} - \frac{1}{12} = \frac{3 - 2}{24} = \frac{1}{24}\text{ per hour}$$
Inlet tap fills the empty tank in $24\text{ hours}$.
High-Yield FAQs & Revision Notes
Why is total work assumed to be 1?
What is the relationship between efficiency and time?
How are wages divided among workers?
How do you handle alternate day problems?
Why do drainage pipes have a negative rate?
How do you solve pairwise problems (A+B, B+C, C+A)?
What is the LCM method for time and work?
What is the formula when worker B leaves k days before completion?
How do you find the capacity of a tank from filling rate in litres/min?
How does this module map to the official RIMC syllabus?
How does this topic relate to the official RIMC syllabus?
| Topic / Concept | High-Yield Exam Rules & Memory Anchor |
|---|---|
| Work Rate | If completed in $n$ days, 1 day's work $= 1/n$. Never add days directly. |
| Product/Sum | Two workers together: $\text{Time} = \frac{ab}{a+b}$. |
| Pairwise System | $2(A+B+C) = (A+B) + (B+C) + (C+A)$. Divide by 2! |
| Departure Before End | $T(1/a) + (T - k)(1/b) = 1$ where $T$ is total project duration. |
| Pipes & Cisterns | Inlet is positive ($+1/t_1$); Leak is negative ($-1/t_2$). |
| Wages Distribution | Divide money in the exact ratio of the work done by each person. |